Lexis/Nexis, SPRINGFIELD, OH
VALUE DELIVERED
A teamwork approach, fast-track completion, and high-quality installation enabled the client to perform its core business more effectively and exploit new opportunities more efficiently, all with less risk to the data upon which its revenues and growth depend.
SCOPE OF WORK
Dynalectric installed a new 15 KV utility service, two 2,000 KW generators, 15 sections of incoming switchgear for internal distribution of 480 V, single-sided uninterruptible power supply (UPS) switchgear, two 500 KVA UPS modules with batteries using static switch technology, four 225 KVA double-ended power distribution units, sixteen 2-panel remote power distribution panels, secondary distribution switchboards and motor control centers to feed preferred alternate power; lighting, power, fire alarm, grounding, lightning protection, and security systems; and a distribution system with high resistive ground.
BACKGROUND
A unit of publishing giant Reed Elsevier Group, the Lexis/Nexis Group offers subscribers in more than 100 countries access to thousands of sources, including newspapers, magazines, journals, and public records, through the internet, CD-ROMs, and books. Culled from more than 16,000 databases, the bulk of its content is legal, business, government, and tax information.
OBJECTIVES
For this "lights out" project, the client sought to construct a state-of-the-art Tier 4 data center, using multiple active power and cooling distribution paths, and redundant components that are concurrently maintainable and fault tolerant. The installation provides dual feed and parallel, closed-transition load shifting capability, virtually eliminating any risk of data loss due to power failure. All equipment can be maintained without scheduled shutdowns, permitting true 24/7/365 operation.
SOLUTIONS
The use of design specialists for efficient high-quality installation, and on-site project managers for hands-on problem and conflict resolution, as well as the application of "method of procedure" (MOP) for early identifi cation of installation methods, procedures, risks, precautions, durations, and other factors, and compilation of pre-function checklists to ensure quality completion of each piece of equipment and system, all contributed to a successful project. Finally, by identifying scheduling milestones early, the company could firmly establish target dates.